The final bills for the dredging of Osborn Island and Mystic Island phase one lagoons have been tabulated, and both are much lower than the original bonding.

The final cost to dredge Osborn Island was $1,698,866, and Mystic Island phase one was $2,538,642. During the Oct. 8 municipal meeting, township Chief Financial Officer Rodney Haines said the figures have been sent to the assessor for certification; then a public hearing will be held on the final assessments.