Tuckerton has started the process to paint the municipality’s only water tower. The $646,900 contract to U.S. Tank Painting of Millstone Township includes painting both inside and outside the water tower.

Unique Scaffolding Systems of Kenilworth started erecting the scaffolding on Monday. The outside will be completed first, weather permitting, said Tuckerton Councilman John Schwartz. The timeline for cleaning and painting the inside of the tower hinges on when the project to remove and replace the waterline that runs beneath Tuckerton Creek is finished.