The $5.9 million project to construct a new spillway in the Tuckerton Route 9 dam will be substantially complete by June 1, said Joe Dee, spokesman for the New Jersey Department of Transportation.

The project is on time and close to budget, with approximately $300,000 in cost overruns due to repairs that had to be made when a sinkhole opened up under a sidewalk near the historic Grist Mill. Adding ADA complaint sidewalk ramps also increased the cost.