Long Beach Township’s project to repair the terminal groin in Holgate is moving forward, with some revision from the original plan. The U.S. Army Corps of Engineers last month approved the municipality’s modified permit application, which includes replacement of the groin’s steel sheet piling component only.

“We’re calling this ‘phase one,'” Mayor Joseph Mancini said Monday. “We have the permit, we went out to bid, and the work is set to begin around Jan. 21. It should be a six-week project.”