It was on time and on budget. On May 10, the Route 9 bridge deck replacement over the Westecunk Creek in Eagleswood Township was deemed completed, and the highway was restored to the normal lane configuration.

The state Department of Transportation’s $2.9 million, federally funded project began preliminary construction in March 2012. NJDOT’s contractor, Ritacco Construction Inc., replaced the structurally deficient bridge deck in stages using pre-cast concrete framed structures, allowing the DOT to maintain one lane of Route 9 in both directions…