The latest schedule from Great Lakes Dredge & Dock Company indicates that the beach replenishment project spanning 31st to 57th streets in the Brant Beach section of Long Beach Township is still on track for completion by the June 15 deadline, according to U.S. Army Corps of Engineers public affairs specialist Stephen Rochette.

“That includes the pumping of sand onto the beach, ” Rochette noted. “There may be some additional work on the fencing and the dune crossovers that continues after that date. ”

He added, “There have been some delays on the project due to mechanical issues with the pumps and a temporary breach in…