An updated project schedule for the initial construction of the Long Beach Island Coastal Storm Damage Reduction project shows the first phase of the beachfill work beginning around April 15 in Beach Haven Park and proceeding toward Holgate.

The original timeline submitted by contractor Great Lakes Dredge and Dock Co. called for beachfill construction to begin in mid-August.