One hundred and seventy of a total of 700 linear feethave beenbulkheaded in the shoreline restoration project on Iowa Court, township engineer Jason Worth told the township committee at its April 25 meeting.

Once the 700 feet are bulkheaded, the stone and rock shelf can be created to bring the marsh back to its 1977 shoreline, Worth said. After fill is added and grasses planted, the project should be completed in June, he said.