The new season of “sprinter, ” a combination of winter weather in spring, has delayed Barnegat Avenue road work in Surf City – again.

Phases three and four of the project, which encompasses 11th Street through Fifth Street, includes completing drainage installation, curb installation, roadwork and paving. Drainage installation was expected to be completed last week with curb installation beginning April 18 and going through May 9, according to Councilwoman Jacqueline Siciliano.