Equipment repairs and a contract option for more sand have shifted the estimated completion for beach replenishment in Harvey Cedars to the start of September. Work began in the borough in late May, and was originally expected to finish around the end of July.

The cutterhead dredge “R.S. Weeks has been down for some time, which pushed the previous completion date … likely into early September,” said Steve Rochette, public affairs officer for the U.S.