The New Jersey Board of Public Utilities has approved two aspects of the South Jersey Gas pipeline proposal at their July 22 meeting: to require the main interconnect to be outside the Pinelands Protected Forest Area zone, and to disallow any new connections to the pipeline where it transverses through the Pinelands.

The B.L. England Generating Station in Beesley’s Point, Cape May County has been ordered to covert its coal-fired electric generator to natural gas by May 2017 or close.